At the moment at the construction site we have done:
- Construction works on 14 buildings;
- Roofing works on 12 buildings;
- Installation of window joinery on 8 buildings;
- Facade works on 8 buildings;
- Flush-mounted electrical installations on 8 buildings;
- Under-floor sanitary installations in 4 buildings;
- Plastering works on 6 buildings;
- Floors on 2 buildings.